Reconstruction of kindergarten „Radost“ Ludbreg

Lead partner: Kindergarten „Radost“

Project duration: 22 months

Total cost of the project: 3.139.093,85  HRK

Program: Rural Development Programme of the Republic of Croatia for the Period 2014-2020

Status of the project: implementation

The results:

Upgrading the building of kindergarten Radost, increasing the standard of living of the local population by increasing the quality of education and pre-school education, increasing the kindergarten capacity for preschool children, increasing the number of children in pre-school education and equalizing development of the town providing adequate spatial and material conditions in kindergartens with harmonized legal regulations

Added value of the project:

The project contributes to the improvement of local services, and reconstruction of kindergarten will improve the quality of organized care, education, and child protection in pre-school education. Realization of the project will solve the lack of current spatial capacities as it will allow for further increase in the acceptance of children, affecting their families and narrowing and widening members of their family community

General description of the project:

Realization of the project will upgrade the building of an existing kindergarten of 497.68 m2, on 2 floors (ground floor, 248.84 m2 and floor 248.84 m2) and will be arranged and equipped with additional facilities in kindergarten; on the ground floor there is a living room, hall, staircase, wardrobe, corridor, sanitary space and covered terrace, and on the 3rd floor office, staircase, storeroom and multipurpose space. Spatial capacity for children will be increased by an additional 220.54 m2 and 219.90 m2 for staff.

Realization of the project will enable the enrollment of 15 children on the waiting list, and the total number of enrolled children would be divided to the groups according to the pedagogical standards and would have 155 children in the whole kindergarten. Such a schedule will enable better quality work for children with smaller groups and 3 new employees.